What’s actually moving in next-generation geothermal

The first commercial enhanced geothermal plant is selling power, but two in three projects are still tests. Here's what the project record shows, milestone by milestone.
The first next-generation geothermal plants are selling power, but two in three projects are still tests.
Next-gen geothermal · 1 of 3Market movementWhat has happened, not what has been promised

Next-generation geothermal has had its biggest year yet. The first utility-scale enhanced geothermal plant is selling power, tech companies are signing for hundreds of megawatts, and drilling methods borrowed from oil and gas are moving out of test wells. For anyone putting capital, people or partnerships into this market, the question is the same one we asked about advanced nuclear. What is actually moving?

To answer it, we went through every enhanced, closed-loop and superhot-rock geothermal project in the Net Zero Insights record, milestone by milestone. We counted only what has happened and is backed by a source, not what has been promised. Here’s what that shows.

Most of the market is still testing

Two in three next-generation geothermal projects on record are pilots or demonstrations. Among the projects built for commercial scale, seven in ten are still at the announcement stage.

Next-gen geothermal projects by furthest milestone on record
Announced or concept55%
Under construction8%
Operating14%
Test completed14%
Suspended or cancelled9%

Share of enhanced, closed-loop and superhot-rock geothermal projects, by the furthest milestone with evidence that it happened. “Test completed” means a pilot or demonstration that ran and ended. Source: Net Zero Insights, November 2026.

The “test completed” line is the one worth a second look. Geothermal has a long history of tests that worked and then stopped: Fenton Hill in New Mexico, which began in the 1970s, Hijiori and Ogachi in Japan, Habanero in Australia, Desert Peak and The Geysers in the US. Each one proved part of the technology. Very few turned into a plant that kept running and selling power.

The first commercial plants are now running

That is what changed this year. Fervo Energy’s Cape Station in Utah declared commercial operation in fall 2026, about two years after construction began, with a first block of 33 MW. Its next phase, and its largest contract, are being built the same way: in repeatable blocks.

Building in blocks: Cape Station, Utah
Phase I · operating from fall 2026
3 × 33 MW

About 100 MW in three identical blocks, the first now selling power under contract

Google agreement · from 2028
4 × 99 MW

396 MW delivered in four tranches under a 15-year agreement

Sources: Fervo Energy, October 2026; Fervo Energy SEC filing, August 2026.

Repeatable blocks make progress easier to track: each block either reaches commercial operation or it doesn’t. They are also how a technology moves from one-off demonstrations towards a build-out that lenders can price.

Plans still move, and not only because of the rock

Germany shows the other side. Eavor’s closed-loop project in Hanover, built to supply heat to the city’s district heating network, had a signed heat contract, a site and a start date. Here’s what happened to it.

One project’s timeline: Hanover-Lahe, Germany
September 2023Heat supply contract with enercity: up to 30 MW, available from 2026Target
October 2024Heat delivery moved to spring 2027, site work to start fall 2025Slip
Early 2026Eavor refocuses as a technology company and steps back from investing in and developing the projectWho carries it
October 2026Project cancelled after no other way to deliver it was foundCancelled

Every target a project has had stays on its timeline, with the source and the cause of each change. Sources: Eavor, September 2023 and October 2024; enercity, October 2026.

Eavor’s flagship site at Geretsried, near Munich, produced its first electricity before the end of 2025, but output from the first loop was low and almost none reached the grid. In October 2026 the company withdrew its drilling rigs while it works on a firm heat offtake agreement before drilling the second loop. In both cases, what stopped the project was who would buy the heat and who would carry the project, as much as what happened underground.

What this means

  • Treat commercial operation as the signal, not pilots. A completed test proves a technique. A plant selling power under contract proves a business.
  • Watch the build pattern. The leaders are building in repeatable blocks of tens of megawatts. Each block is a milestone you can check.
  • Check who carries the project. A heat or power contract only holds if someone owns, funds and runs the plant behind it.

In part 2, we look at who is setting the pace: the buyers signing contracts, and what those contracts actually commit them to.

Build on it

Build your own project tracker.

Every project, milestone, target date and slip behind this article is structured, sourced data you can work with directly. Teams use it to:

  • Check each month which milestones happened and which target dates moved, for the projects they follow
  • Screen projects by technology, country, scale and stage before a partner meeting or site visit
  • Pull a project’s full timeline, with sources, into a memo or board paper

Work with it in your own AI tools through our MCP connector (Claude, ChatGPT or Copilot), in Barry, our research assistant, or as Excel workbooks. It’s part of Signals by Net Zero Insights.

InvestorsBuild your own pipeline screen and diligence checks.
CorporatesBuild your own partner scouting and peer tracking.
Book 30 minutes to set it up on your market

We’re working with a small group of design partners on our advanced nuclear and next-gen geothermal data.

More Insights

Four gaps where demand in next-generation geothermal is running ahead of supply: developers beyond the leader, drilling, heat buyers in Europe, and repeatable commercial plants.
Utilities, not tech companies, sign most geothermal power deals, and they sign firm ones. Here's who is buying, on what terms, and why one developer