What’s actually moving in advanced nuclear

Construction starts have picked up sharply, but most of the advanced nuclear pipeline is still on paper. Here's what the project record shows, milestone by milestone.
Construction is picking up, most of the advanced nuclear pipeline is still on paper: 70% of projects announced, 18% under construction, 5% operating, 6% stalled.
Advanced nuclear · 1 of 3Market movementWhat has happened, not what has been promised

Advanced nuclear has never had more announcements. New reactor designs, new sites, new partnerships with tech companies: most weeks bring another one. For anyone putting capital, people or partnerships into this market, the question that matters is simpler. What is actually moving?

To answer it, we went through every advanced fission and fusion project in the Net Zero Insights record, milestone by milestone. We counted only what has happened and is backed by a source, not what has been promised. Here’s what that shows.

Most of the pipeline is still on paper

Seven in ten advanced nuclear projects are still at the announcement or concept stage. Fewer than one in five has a construction start on record. Only two advanced reactors are running today, and neither is in Europe or North America: China’s HTR-PM demonstration plant and Russia’s floating Akademik Lomonosov.

Advanced nuclear projects by furthest milestone on record
Announced or concept70%
Final investment decision1%
Under construction18%
Operating5%
Suspended or cancelled6%

Share of advanced fission and fusion projects, by the furthest milestone with evidence that it happened. “Operating” includes fuel and manufacturing facilities as well as reactors. Source: Net Zero Insights, November 2026.

The gap at the investment-decision stage is worth a second look. Very few projects have a final investment decision on record, and none has reached financial close. That suggests most of what is being built is funded by developers, governments or strategic backers, not by the project financing that usually marks a market’s move from pilots to infrastructure.

The pace of construction has changed

Look at when construction started and a different picture appears. As many advanced nuclear projects broke ground in 2025 and 2026 as in the eighteen years before.

Construction starts on record, by period
2007 to 2024 · 18 years
Half

of all advanced nuclear construction starts on record

2025 and 2026 · 2 years
Half

of all advanced nuclear construction starts on record

Construction starts with evidence that they happened. Source: Net Zero Insights, November 2026.

What is being built tells you more than how much. In the US, most new construction is pilot and demonstration reactors, and a growing share is fuel: TRISO fuel production and uranium enrichment. Commercial-scale reactor construction is still rarer, and most of it is outside the US. Canada’s first BWRX-300 small modular reactor at Darlington, under construction since May 2025, is the clearest Western example.

Dates are the softest data point

Target dates move more than anything else in this market. Of the projects that have at some point pointed to commissioning between 2026 and 2028, nearly half have not started construction or have been suspended. Earlier targets, some more than a decade old, sit in the record unmet.

TerraPower’s Natrium plant in Kemmerer, Wyoming, shows how it happens.

One project’s timeline: Natrium, Kemmerer, Wyoming
Original targetFinished by 2028Target
December 2022Delay of at least two years announcedSlip
CauseHALEU fuel: the only commercial supplier was RussianFuel supply
June 2024Construction startsMilestone

Every target a project has had stays on its timeline, with the source and the cause of each change. Sources: CNBC, December 2022; TerraPower, June 2024.

That’s why we keep every target a project has ever had, and the reason it moved, rather than overwriting the old date with the new one. The history of a project’s dates is often the best guide to how much to trust the current one.

What this means

  • Treat construction starts as the signal, not announcements. A design is real when concrete is poured, and that is now happening faster than at any point on record.
  • Watch fuel. The best-known slip in the market traced back to fuel supply, and a growing share of new US construction is fuel capacity.
  • Discount target dates until a project is building. Before construction starts, a commissioning date is a plan, not progress.

In part 2, we look at who is setting the pace: the buyers signing contracts, and what those contracts actually commit them to.

Build on it

Build your own project tracker.

Every project, milestone, target date and slip behind this article is structured, sourced data you can work with directly. Teams use it to:

  • Check each month which milestones happened and which target dates moved, for the projects they follow
  • Screen projects by technology, country and stage before a partner meeting or site visit
  • Pull a project’s full timeline, with sources, into a memo or board paper

Work with it in your own AI tools through our MCP connector (Claude, ChatGPT or Copilot), in Barry, our research assistant, or as Excel workbooks. It’s part of Signals by Net Zero Insights.

InvestorsBuild your own pipeline screen and diligence checks.
CorporatesBuild your own partner scouting and peer tracking.
Book 30 minutes to set it up on your market

We’re working with a small group of design partners on our advanced nuclear and next-gen geothermal data.

More Insights

Track the latest Climate Tech investment activity, with 230 deals and 6 new funds recorded over the past two weeks across drone delivery, AI chips,
Fuel supply, the step from pilot to commercial plant, buyers beyond data centers, and Europe: four gaps in the advanced nuclear market where new opportunities
Contracts are arriving fast, tech companies are the main buyers, and nearly half the deals are for fuel, not power. Here's who is driving advanced